Launch and Full Mobilization: Customer Needs Come First
The No. 1 and No. 2 condensers for the Hejin project had the shortest project cycle and fastest commissioning in the company's history. After receiving the order, all departments collaborated efficiently. The project was launched, all relevant departments mobilized, product delivery was completed within 40 days, and commissioning delivery was completed within 60 days.
Initial operation began on December 14. All data were normal, and the 20°C supply-and-return water temperature difference met the design target.
Project launch
After receiving the project in early October, the Project Planning Department immediately launched the work, assigned responsibility for organization, participation, coordination, and manufacturing, convened a special project meeting, prepared a detailed follow-up plan and schedule, identified key difficulties in advance, and coordinated departments around the principle that customer needs come first.
Design taking the lead
The Design Department faced both an extremely short design cycle and unusually demanding technical standards. Delivery was required in just over one month, while the tube-side design pressure reached 1.6 MPa, requiring a new non-standard design.
The department broke with conventional approaches and introduced several key innovations: a single-inlet, single-outlet, four-pass layout to optimize space and heat-transfer efficiency; strict application of GB/T 150 and GB/T 151 with strength checks for tube sheets and other core components; a head seal with a maintenance manhole on the water side to combine lightweight construction with high-integrity sealing; and reinforcing ribs to optimize the load path for the large blind-plate force at the neck and ensure structural safety.
During execution, the team gave up the National Day holiday and worked intensively under coordinated leadership and resource allocation. All high-quality construction drawings were completed within one week, on October 15, safeguarding the critical milestone.
Production organization
After the drawings were finalized, subsidiary Sichuan Niukeli Technology Co., Ltd. used inventory material to cut the intermediate tube sheets, completing all cutting on October 17 and moving immediately into welding and machining. Tack welding and transfer to machining were completed in only two days.
At the same time, the Digital Intelligence Department supported process implementation and completed finalization quickly. The Manufacturing Department and Sichuan Niukeli then launched production. The short tube sheets, the most difficult supporting items, were completed by October 30.
The Manufacturing Department carefully organized end-tube-sheet machining and arranged internal and external resources in the required production sequence. Front and rear tube sheets for Units 1 and 2 were completed in early and mid-November, with the rear tube sheet completed on November 16, establishing the basis for accelerated shell fabrication.
Dedicated teams worked in sections according to the process and overall schedule. All components were shipped within November. After shipment of Unit 1, two service personnel were sent to site to support installation and provide guidance.
Accelerated tube-sheet manufacturing
Other components
No. 1 condenser shell shipment
No. 2 condenser shell shipment
From design coordination and advance material procurement to production organization, the entire chain treated the project as a priority. It achieved several breakthroughs: the shortest project cycle, the most demanding design, the tightest compression of all stages, and seamless end-to-end coordination.
Through close cooperation among departments, the project was delivered on time, operated safely, met design requirements, and achieved multiple technical breakthroughs. It demonstrated the team's technical adaptability under high-pressure, short-cycle conditions and the company's efficient execution, while applying the customer-first principle throughout and accumulating valuable experience for similar difficult projects.