HAIEN ENERGYCompany News

Aftermarket Business Feature: Company's First On-Site Reassembly of a 1,000 MW Modular Steam Turbine Successfully Delivered

The company's on-site reassembly project for the intermediate-pressure steam-turbine module of Phase III, 2×1,000 MW, at Jinkong Power Tongying Thermal Power (Shanxi) Co., Ltd. recently passed joint acceptance by all parties and was formally delivered for the power-construction installation stage.

This is a key main-unit installation process for the supporting power source of the ultra-high-voltage transmission project serving the new-energy base in northern Shanxi's coal-mining subsidence area. It was also a quality and technology improvement project for the company's Aftermarket Business Division.

Successful completion demonstrates renewed industry recognition of the company's technical and delivery capability in field services for core components of million-kilowatt ultra-supercritical units.

Rotor runout inspection; combined steam-path inspection

Article image 1 of 7
Article image 2 of 7

Phase III is a key energy project in Shanxi Province with total dynamic investment of nearly RMB 7.9 billion. Once completed, it will transmit electricity to load centers in Beijing, Tianjin, and Hebei through the Datong-South Tianjin UHV channel and provide district heating for 28 million square meters in Datong's Yungang District.

The intermediate-pressure module is a core energy-conversion component. Dense cross-operations, a complex site environment, and a tight schedule imposed stringent requirements for safety, technical capability, and quality management.

Lower half of casing positioned

Article image 3 of 7

Anchoring the safety baseline and building end-to-end protection

The project team treated safety as its top priority. In response to risks from multi-party cross-operations, high-elevation lifting, and confined-space work, it prepared a special safety construction plan in advance and strictly implemented the 'two permits and three systems' requirements and on-site supervision for hazardous work. The project achieved zero safety accidents and zero rule violations.

Overcoming technical difficulties with precise processes

To address the complex reassembly process and stringent precision requirements of the ultra-supercritical intermediate-pressure module, the technical team coordinated with the equipment manufacturer in advance, repeatedly checked factory data against site installation parameters, and optimized procedures for steam-path clearance adjustment, shaft alignment, and casing load distribution.

Key fit-clearance error was held within 0.02 mm, and cat-paw load-distribution deviation was controlled within half of the allowable design range. All installation data met design standards and industry codes, achieving defect-free delivery of the reassembly work.

Strengthening coordination and responding precisely to milestone needs

Inner-casing assembly; diaphragm-carrier assembly

Article image 4 of 7
Article image 5 of 7

To meet the schedule required by the owner and EPC contractor, the team coordinated with the equipment manufacturer one month in advance, confirmed module-supply parameters and site reassembly conditions, and completed advance work such as foundation reinspection and tool preparation.

It also established a daily scheduling mechanism with the installation contractor and dynamically optimized cross-work areas. Without compromising quality or safety, the team maintained the August 27 delivery milestone and secured valuable time for subsequent turbine commissioning.

Hot-tightening elongation measurement of the outer casing; final external-value measurement

Article image 6 of 7
Article image 7 of 7

Successful completion of the intermediate-pressure module reassembly embodies the company's service principles of safety first, quality foremost, and customer priority. The company will continue to develop field technical services for thermal-power units and support major energy projects with professional technical capability and rigorous management, contributing to regional energy security and the dual-carbon goals.

END