Design-Led and Schedule-Driven: Construction of the Southern Xinjiang Energy Group EPC Project Advances Steadily

Design-Led and Schedule-Driven

Peak-shaving facilities strengthen the foundation; green heat supply provides solid support.

The EPC project being executed by the company, 'Peak-Shaving Facilities Supporting the 2×30 MW Back-Pressure Units in the Industrial Park of Regiment 1, Division 1, Southern Xinjiang Energy Group,' is a key combined-heat-and-power infrastructure project promoted by the Xinjiang Production and Construction Corps. Southern Xinjiang Energy Group is the owner. The project is currently in an intensive construction phase and has recently reached another key foundation milestone.

Project groundbreaking ceremony

Article image 1 of 6

The project comprises two 30 MW back-pressure cogeneration units, three 190 t/h high-temperature and high-pressure pulverized-coal boilers, two 30 MW back-pressure turbine-generator units, and two static-excitation, three-phase, two-pole synchronous generators, together with flue-gas desulfurization, denitrification, and dust-removal systems.

Following the combined-heat-and-power principle of determining power generation according to heat demand, the back-pressure turbines supply heat or industrial steam directly through medium- and low-pressure exhaust steam.

The stated overall thermal efficiency can exceed 80%, because exhaust heat is used directly, reducing energy waste and making energy supply to Division 1 more stable, greener, and more economical.

Industrial park entrance

Article image 2 of 6

Project launch: one contract, one responsibility

On August 14, 2026, the company, as consortium leader, formally signed the EPC contract after reaching agreement with consortium member Shandong Sunshine Engineering Design Institute Co., Ltd. and Alar Boqi Intelligent Environmental Protection Technology Co., Ltd.

The consortium brings together the company's equipment-manufacturing capabilities and the power engineering institute's design capabilities, providing an organizational foundation for the full process from preliminary design to final delivery.

The scope covers all work required for normal project operation, from preliminary design through the end of the warranty period, so that responsibility remains consistent from the first line on the drawing to stable unit operation at completion.

Engineering design review meeting

Article image 3 of 6

On-site report: foundation construction enters a key stage

By the date of this progress update, two key foundation milestones had been achieved.

Turbine bottom-raft scaffolding and formwork completed

The turbine island is the heart of the unit and has high loads, stringent precision requirements, and complex embedded items. Scaffolding and formwork for the bottom raft have been completed. The geometric dimensions, elevation, and load-transfer path of the raft are ready for acceptance, preparing for reinforcement installation, embedded-item installation, and mass-concrete placement.

Article image 4 of 6

Independent foundation for the evaporative condenser completed

As an important supporting device in the peak-shaving system, completion of the evaporative condenser's independent foundation means that earthwork excavation, the blinding layer, reinforcement, formwork, and concrete placement in the area have been closed out in accordance with the design. This creates the conditions for equipment positioning, upper-structure construction, and embedded-item installation.

Article image 5 of 6

These milestones show that the project has moved from site preparation into main structural construction, while also testing the consortium's coordination efficiency across design, procurement, and construction.

Project controls: advance schedule while safeguarding quality

Schedule: manage the critical path around turbine raft pouring, the evaporative condenser's upper structure, and equipment arrival to reduce interruptions between processes.

Quality: implement temperature control for mass concrete, verify embedded-item accuracy, and conduct concealed-work acceptance with the goal of first-time quality.

Safety: strengthen on-site supervision of work at height, formwork support systems, lifting operations, and temporary power.

Coordination: use the integrated design, manufacturing, and construction advantages of the consortium to review equipment interfaces early and avoid rework.

Winter construction: plan winter measures in advance for the local climate to protect the quality of concrete and masonry work.

Turbine baseplate reinforcement installation

Article image 6 of 6

Continued progress: from blueprint to reality

From signing the contract to completing foundation structures, the EPC project is advancing according to the planned milestones. Foundation construction is now fully under way, turning the drawings into reality step by step.

Since project launch, the consortium has followed the principles of equality, voluntariness, fairness, honesty, and good faith, coordinated construction resources, refined milestone controls, and promoted implementation while safeguarding safety and quality.

All construction tasks are progressing steadily. The consortium will continue to comply strictly with construction standards, target a high-quality benchmark project, and strive to deliver a project that reassures the owner and benefits the industrial park.

Further progress will be released through the company's official channels.